Monterey Bridge Project on Schedule

 
 

The Monterey Bridge project is moving along despite the water issues experienced in April.

Bret Smiley, construction manager with United Consulting, said there was a bit of a flooding issue at the southern end of the bridge project, but that isn’t affecting the work being done this week on the north side of the bridge. The south side of the bridge project had been underwater and the workers have been working around that issue. LaPorte Construction built up a makeshift berm to help with erosion issues and to push back the river water.

Rain dates were built into the original construction schedule so Smiley noted the project is on schedule. They are drive piling the north side of the bridge so beams can be set this week and situating the crane so it can safely operate. Smiley said the ground is swelled with water and unstable so they are creating a safe platform for the crane.

Smiley said the retaining walls will be built in the next week or so.