Monterey Bridge Project on Schedule

  
 
After a few weeks of battling high water issues, the crew working on the Monterey Bridge project is moving right along.

Bret Smiley of United Consulting reported that the beams have been set and the crews are placing decking at this juncture of the project. Overhang jacks are being installed along the outside beams and they are installing decking on them as well. Once the deck is completely prepared, the next step will be the placement of rebar throughout the deck.

The project appears to be on schedule and the project should be completed in October.