Marshall County Commissioners Receive Update on Projects

  
 

The Marshall County commissioners received an update on the 7th Road project and the Metronet project Monday morning.

USI Consultant’s Bart Trester is the project manager and said the 7th Road project is moving along.

“The contractor has begun the soil stabilization of the sub-grade and should finish from Linden Trail to Seltenright Ditch by the end of the week. This will actually allow them to put in under drains and hopefully begin paving toward the end of the week. They won’t put surface down this year. Traffic has been running on a temporary lane allowing the contractor to construct phase two of the roundabout on Michigan Road. Traffic will be switched to phase three at the end of this week or early next week. They will be running through the center of the roundabout at this time allowing them to construct phase three which is the east side up to Zimmer Ditch,” said Trester.

Continue reading