Marshall County Commissioners Review Airport Comprehensive Plan

  
 

Plymouth Airport Manager Dave Lattimer presented the Marshall County Commissioners with the board’s comprehensive plan this week.

One of the projects that the board is anticipating is the widening of the runway, which Lattimer says is set to begin in the next several months.

“That involves widening our runway from 60 feet to 75 feet and rebuilding 4,400 feet of pavement,” Lattimer explained. “The next phase is to lengthen the runway. The magic number for an airport our size is 75 feet wide and 5,000 feet long.”

Continue reading

Plymouth Airport Board Moving Forward to Obtain Weather Station

 
 

The Plymouth Aviation Board will be moving forward in obtaining a weather station.

Dave Lattimer told the Marshall County Council on Monday morning that it’s highly probable that the green light will be given for a weather station after several other improvements are made.

Lattimer explained that the runways need to be extended and widened and two taxiways from the ramp to the runways need to intersect at a “T” instead of at a 45 degree angle. The staff will also need to extend the taxiways. Insurance will also need to be adjusted. All of those improvements need to be done before the FAA will approve the Plymouth Airport for a weather station.