The North Judson-San Pierre School Board had a project update during their meeting this week.
Superintendent Dr. Annette Zupin announced the new elementary gym floor will be laid down beginning October 10. Once the gym is finished, the floor will need to sit for three weeks before it can be used. The hope is for the work to be done by Christmas.
The new roof at the Elementary School is almost complete. Dr. Zupin said the roof should be done within four weeks.
The overall project includes the construction of a new gym with an opportunity to use the old gym as a way to expand the cafeteria, include a multi-purpose room, collaboration room, conference room, and a faculty dining/meeting room. With that includes the relocation of playground equipment and the renovation of the Elementary School as a whole.