The Marshall County Commissioners will consider a change order request from USI Consultants’ Bart Trester when they meet today. Trester oversees the 7th Road project and the roundabout project on North Michigan Road in Plymouth. Trester indicated earlier this month that crews are waiting for word from the state to move ahead, barring any more issues with the HMX mix design. The mix of aggregate and asphalt binder is causing buckling pavement in other locations across the state. Crews are awaiting final approval of the combination to install the mix.
Construction on 7th Road Project Continues
The 7th Road project in Plymouth should be complete by the end of June.
Project Supervisor Bart Trester from USI Consultants told the Marshall County Commissioners on Monday that the center of the roundabout is open to traffic in order for construction to occur on the east and west third of the circular intersection. Crews will return the traffic pattern to travel around the roundabout when that phase is complete. The project is anticipated to be done by the end of June.
Change Orders Approved for 7th Road Project
The 7th Road construction project has been on hold all winter, but once the weather breaks workers will be busy to finish the project. It was anticipated to be complete last year.
Bart Trester from USI Consultants told the Marshall County Commissioners that several issues delayed the project including unsuitable soils and piling issue for the bridge. He presented a change order for the project once things get moving again.
Metronet Project Done, 7th Road Project Awaiting Completion
This week, the Marshall County Commissioners approved and signed paperwork to complete the acceptance of the Metronet project along Glen Overmyer Drive. The work ended on Nov. 12 with all punch list items checked off the list. The installation of conduit for the three phases of the Metronet project is now complete.
The conduit will house dark fiber capable of distributing high-speed internet to business and industry in Plymouth. The conduit was installed in the city limits and along old U.S. 31 through LaPaz, LaVille, Lakeville and into South Bend. LaVille School Corporation and Hoosier Racing Tire have already lit dark fiber to begin using the product.
Marshall County Commissioners to Meet Tuesday
The Marshall County Commissioners will not meet today as the county employees will observe Martin Luther King, Jr. Day.
When they meet tomorrow, the highway department heads will have updates on the wetland mitigation issue and the mill pond dam. Highway Administrator Laurie Baker and Supervisor of County Highways Jason Peters will also have pug mill estimates and bid specifications for a loader.
Bart Trester from USI Consultants will present a fiber-optic conduit certification of completion for Glen Overmyer Drive in connection with the Metronet project. Curt Fey from Legal Shield will have a presentation, and the commissioners will discuss the 2015 covered bridge certification.
Road Construction Project in Marshall County on Hold
The 7th Road project in Marshall County will not be completed this year.
The project supervisor overseeing the construction, Bart Trester, told the Marshall County Commissioners that the current state of the project on Michigan Road will remain through the winter.
“The traffic has been running on phase three section of the roundabout and will probably remain like this through the winter,” said Trester. “The contractors finished placing the HMA base and intermediate lifts along the main line from Seltenright Ditch to Linden Trail and the HMA base from Seltenright Ditch to the roundabout. Due to weather limitations, the contractor will more than likely shut down operations for the winter. They have opened Lilac Road and Linden Trail for thru-traffic for over the winter.”
Marshall County Commissioners to Meet Today
The Marshall County Commissioners will meet today where Bart Trester from USI will give an update on the 7th Road construction project, the Metronet project and work on the Jefferson Street bridge.
The commissioners will also have the second reading of an ordinance regulating construction setbacks at Pretty Lake. Plan Director Ralph Booker explained in a public hearing that the Pretty Lake Homeowners Association approved a change where new construction at the lake would need to be a 45 foot setback from an 789.0 elevation line.
Weather Delays Jefferson Bridge Opening
It will take a couple of more days to open the Jefferson Street bridge in Plymouth.
Marshall County Supervisor of County Highways Jason Peters told WKVI News that weather has delayed the completion of bridge work. The projected reopening date is now Wednesday.
Bart Trester from USI Consultants told the Marshall County Commissioners last week that the remaining items on the checklist include sidewalks and curbs. Crews also want to reseal the bridge deck to complete the project.
Three Major Projects in Marshall County on Track for Completion This Year
Bart Trester from USI Consultants updated the Marshall County Commissioners on a few projects in the county.
Trester said traffic is running on the third phase of the roundabout north of Plymouth on Michigan Road as part of the 7th Road project.
“The contractor is in the process of starting work from the roundabout to the bridge over the Seltenright Ditch in hopes of opening the roundabout this year. Contractors also finished the majority of the bridge construction over Seltenright Ditch with only railing items to be completed,” said Trester.
Marshall County Commissioners to Meet Today
The Marshall County Commissioners will receive updates on three major construction projects when they meet this morning.
Bart Trester from USI will have status updates on the 7th Road construction project, the Metronet project and the Jefferson Street Bridge rehabilitation project.
The commissioners approved paperwork at their last meeting to call sections of the Metronet project substantially complete. Supervisor of County Highways Jason Peters told WKVI News last week that Beer and Slabaugh is working on the east end of the Jefferson Street bridge and that road should be open at the end of next week.
Marshall County Council Approves Appropriation for Metronet Project
The Marshall County Council members discussed an additional appropriation for the Metronet project Monday morning.
The amount was for $250,000 out of the Rainy Day Fund which is the amount St. Joseph County is expected to pay for the project.
Auditor Penny Lukenbill explained that Trinity Health sent in $125,000 for their portion of the cost in August which was appropriated last month. The county is anticipating St. Joseph County’s portion of $250,000 this week. Lukenbill stated that she wants to be prepared for when that happens.
Marshall County Commissioners Receive Update on Projects
The Marshall County commissioners received an update on the 7th Road project and the Metronet project Monday morning.
USI Consultant’s Bart Trester is the project manager and said the 7th Road project is moving along.
“The contractor has begun the soil stabilization of the sub-grade and should finish from Linden Trail to Seltenright Ditch by the end of the week. This will actually allow them to put in under drains and hopefully begin paving toward the end of the week. They won’t put surface down this year. Traffic has been running on a temporary lane allowing the contractor to construct phase two of the roundabout on Michigan Road. Traffic will be switched to phase three at the end of this week or early next week. They will be running through the center of the roundabout at this time allowing them to construct phase three which is the east side up to Zimmer Ditch,” said Trester.
Marshall County Commissioners to Meet Today
The Marshall County commissioners will meet today with a host of items to discuss.
Bart Trester of USI will provide the commissioners with an update on the 7th Road project and the Metronet project. The Metronet project is ahead of schedule while the 7th Road project continues. An update on the Jefferson Street bridge will also be provided by a USI representative.
Ward Byers from Court Services will be before the board for approval of an employment contract and Stacy Richer will have a request to vacate a street on county-owned property.
Conduit Installation for Metronet Project in Marshall County on Schedule
The Metronet project in Marshall County is on schedule.
Marshall County Auditor Penny Lukenbill told WKVI News that Bart Trester of USI reported to the commissioners on Tuesday morning that the county’s portion of the project is 85 to 90 percent complete. The hang-up right now surrounds the construction along Kern Road and Ireland in South Bend with the new U.S. 31 project. The company continues to work with INDOT in moving along that portion of the Metronet project.
Marshall County Commissioners to Meet Today
The Marshall County Commissioners will meet today.
Plan Director Ralph Booker will present the commissioners with a Brownfield Assessment grant agreement. The Brownfield Assessment grant gives the county a chance to identify abandoned buildings, vacant fields and problematic areas to rehabilitate them and clean up the sites. The grant money would repair blighted areas by preparing them for potential business sites. The money would also be used to test areas for possible contaminates. Continue reading
7th Road, Metronet Projects Continue in Marshall County
The Marshall County Commissioners received an update on two ongoing construction projects.
Bart Trester, project supervisor for the 7th Road project, said the project is on schedule to finish this year.
“The contractors have completed the removal of the unsuitable soils and are backfilling with the borrowed material along the project limits. With that done, the contractors have been able to upgrade the main line and cut ditches along the project limits. They have completed the installation of the box culvert at Zimmer Ditch and a temporary lane has been constructed. Traffic will be switched over and this will allow the contractor to begin construction on the roundabout on Michigan Road. Pile driving issues on the Seltenright Ditch are on hold as we’re waiting for the contractor to return to the project. In talking with the designer, we should be able to lighten driving requirements so we don’t have to drive them so deep,” explained Trester.
Marshall County Commissioners to Meet Today
The Marshall County Commissioners will meet today at 8:30 a.m. ET.
Emergency Management Agency Director Clyde Avery will update the commissioners on the emergency plan. During the last commissioners meeting, Avery explained that the emergency plan was changed after events during the winter season. Department heads said working with the EMA Director by way of virtual means would work better, but Avery believes that may not be the best solution – especially if electricity and internet services are not available.
Major Projects Moving Along in Marshall County
The Marshall County Commissioners received an update on two major construction projects in the county from USI’s Bart Trester. Trester is the project manager of the 7th Road and the Metronet projects.
Trester explained that unsuitable soils are being removed from portions of the 7th Road project. The soils were found in different locations in the project and weren’t detected in soil borings conducted prior to the project. The removal of the soils was quite costly. The commissioners approved a change order of over $500,000 at a previous meeting to meet that requirement. Crews are borrowing suitable soils between Lilac Road and Seltenright Ditch.
Marshall County Commissioners to Meet Today
The Marshall County Commissioners will meet in regular session this morning with several items on the agenda.
Bart Trester from USI will give the commissioners an update on two county projects. The 7th Road project recently had a hiccup when unstable, organic soil was found. It had to be dug up and removed from the area.
Marshall County Commissioners Approve Large Change Order
The Marshall County Commissioners approved a rather large change order during their meeting Monday morning for the 7th Road project.
At the previous meeting, Bart Trester from USI told the commissioners that unsuitable soil was found along the project route. Upon testing, it was found that the soil had a high organic compound which is not stable for construction. A soil bore had been conducted prior to the start of the project, but the soil composition was found to change frequently along the route. Trester explained that the organic soil needs to be removed.