The deadline for relocation expenses stemming from the Monterey Bridge construction project has come and gone, according to United Consulting’s Jeff Larrison. He told the county commissioners that he received a notice explaining the the deadline has passed and some expenses still had not been turned in, raising the question of whether or not the commissioners would like to still allow those expenses to be filed.
Monterey Bridge Project Coming Along
The Monterey Bridge project is moving along.
Bret Smiley, construction manager with United Consulting, told WKVI that concrete has been poured this week. The rail wall, the bridge deck and approaches have been poured. He said he did testing and it was the smoothest concrete pour that he’s been privy to.
Monterey Bridge Project on Schedule
The Monterey Bridge Project is expected to be completed before the Nov. 29 completion date.
Bret Smiley, construction manager with United Consulting, said the construction crews have installed the Stay-in-Place metal decking. Continue reading
Monterey Bridge Project on Schedule
After a few weeks of battling high water issues, the crew working on the Monterey Bridge project is moving right along.
Bret Smiley of United Consulting reported that the beams have been set and the crews are placing decking at this juncture of the project. Overhang jacks are being installed along the outside beams and they are installing decking on them as well. Once the deck is completely prepared, the next step will be the placement of rebar throughout the deck.
The project appears to be on schedule and the project should be completed in October.
Monterey Bridge Project on Schedule
The Monterey Bridge project is moving along despite the water issues experienced in April.
Bret Smiley, construction manager with United Consulting, said there was a bit of a flooding issue at the southern end of the bridge project, but that isn’t affecting the work being done this week on the north side of the bridge. The south side of the bridge project had been underwater and the workers have been working around that issue. LaPorte Construction built up a makeshift berm to help with erosion issues and to push back the river water.
Rain dates were built into the original construction schedule so Smiley noted the project is on schedule. They are drive piling the north side of the bridge so beams can be set this week and situating the crane so it can safely operate. Smiley said the ground is swelled with water and unstable so they are creating a safe platform for the crane.
Smiley said the retaining walls will be built in the next week or so.