Winamac Wastewater Superintendent, Brad Zellers, came before the Winamac Town Board this week to report on the $5.2 million dollar sewer separation project. Zellers said the project is actually ahead of schedule and that all of the pipes are in the ground. The installation of some manholes and catch basins have yet to be completed. Also to be determined is if the compaction is adequate to pave the streets. IDEM rules are that the pipes must be in the ground 30 days before the paving can begin, which would put it in the middle of November.
Starke County Mint Farmer to be Sentenced Wednesday
Mint farmer, Mike Materna, of Hamlet, will be sentenced in U.S. District Court on Wednesday, October 5th. He plead guilty to one count of Discharge of Pollutants without a Permit in violation of the Clean Air Act. He reportedly admitted in court that he discharged hot water into a ditch without the proper permit.