Upgrades to North Judson’s wastewater facilities are now complete. The town council approved the certificate of substantial completion last week, along with final pay applications.
Continue reading
Upgrades to North Judson’s wastewater facilities are now complete. The town council approved the certificate of substantial completion last week, along with final pay applications.
Continue reading
North Judson’s wastewater project continues to move along. Sarah Prizio with Commonwealth Engineers told the town council last week that crews had finished installing the storm sewer along Railroad and Franklin streets, while work on the portion on Main Street was wrapping up.
Continue reading
North Judson’s wastewater project is expanding slightly. The town council approved a pair of change orders last week.
Continue reading
The Town of North Judson will have a required audit of its water infrastructure completed at no cost. The Indiana Finance Authority is now asking utilities to have a water loss audit done each year and get it validated every two years, according to Sarah Prizio with Commonwealth Engineers.
Continue reading
Commonwealth Engineer Intern Sarah Prizio recently informed North Judson Town Council members about some additional funds that will be available for future use.
She noted that as Commonwealth reps were finishing up the Town’s asset management plan, it was discovered that they’re about $20,000 under budget for inspection services.
Continue reading
North Judson Town Council members were introduced to another point of contact from Commonwealth Engineers when members met last Monday.
Continue reading
When the North Judson Town Council met last Monday, CommonWealth Engineer Intern Sarah Prizio shared that there was recently a change to who is representing their firm on site.
Continue reading
An update on the North Judson’s wastewater treatment plant project was provided to Town Council members when they met Monday night.
Continue reading