The Knox Board of Works has approved the final payout for the Wastewater Treatment Plant project, even though some issues remain. After months of negotiations with Thieneman Construction, the board approved a final change order during a special meeting last week. It accepts Thieneman’s offer of two consecutive five-year maintenance bonds, since a concrete pouring mishap last year could make the basement wall more prone to leaks.
Continue readingKnox Wastewater Project Contractor Objects to City’s $7,000 Deduction
The Knox Wastewater Treatment Plant project has hit another snag. Thieneman Construction has objected to the city’s deduction of $7,000 from its payment, following a concrete pouring accident last year that led to the need for an unanticipated cold joint in the basement wall.
Continue readingKnox Board of Works Approves Final Payment to Wastewater Project Contractor, Despite Problems
It turns out the Knox Wastewater Treatment Plant improvement project wasn’t as close to being done as previously thought. After numerous delays and cost overruns, it appeared last month that the only thing remaining was some final wiring work.
Continue readingKnox Board of Works to Hold Code Enforcement Hearing this Morning
The Knox Board of Works will hold hearings on code enforcement issues this morning. Public hearings are scheduled for 504 East Culver Road, 1498 East John Street, and 342-344 West Spruce Drive. Last month, Director of Building and Code Compliance Kenny Pfost told board members that the biggest concern at the time was junk vehicles.
Continue readingKnox Wastewater Plant Project Wrapping Up
Work at the Knox Wastewater Treatment Plant was set to reach final completion Wednesday, 12 days after the most recent deadline. Engineer Steve Henschen with Jones Petrie Rafinski says that when the board of works had an executive session last Monday, Thieneman Construction still had about 15 to 20 items remaining on the punch list, most notably, the installation of an overhead door.
Continue readingKnox Board of Works Approves Another Extension for Wastewater Plant Project
Completion of the Knox Wastewater Treatment Plant project has been delayed yet again. The board of works Wednesday reluctantly agreed to extend substantial completion to the week of October 12 and final completion to November 12.
Continue readingWork Progressing at Knox Wastewater Treatment Plant
Work is picking up at the Knox Wastewater Treatment Plant. That’s according to Engineer Steve Henschen with Jones Petrie Rafinski. He told the board of works last week that the building shell is up, and the building is almost completely enclosed. Henschen added that work inside the building was proceeding at a “rapid pace.”
Continue readingKnox Board of Works Grants 56-Day Extension for Wastewater Plant Upgrades
The Knox Wastewater Treatment Plant project has officially been extended by 56 days, but not without some concerns from the board of works. Board members approved the extension during a special meeting Tuesday.
Continue readingKnox Board of Works Not Ready to Give 56-Day Extension for Wastewater Project
The Knox Board of Works wants more information before agreeing to give Thieneman Construction more time to finish improvements to the wastewater treatment plant. Engineer Steve Henschen with Jones Petrie Rafinski told board members Wednesday that Thieneman has asked for a 56-day extension.
Continue readingCost of Knox Wastewater Plant Upgrades Increases by Almost $46,000
The Knox Wastewater Treatment Plant improvement project looks like it’ll be over budget and behind schedule. Last week, the board of works approved a change order increasing the cost by almost $46,000.