The Marshall County Commissioners received an update on two ongoing construction projects.
Bart Trester, project supervisor for the 7th Road project, said the project is on schedule to finish this year.
“The contractors have completed the removal of the unsuitable soils and are backfilling with the borrowed material along the project limits. With that done, the contractors have been able to upgrade the main line and cut ditches along the project limits. They have completed the installation of the box culvert at Zimmer Ditch and a temporary lane has been constructed. Traffic will be switched over and this will allow the contractor to begin construction on the roundabout on Michigan Road. Pile driving issues on the Seltenright Ditch are on hold as we’re waiting for the contractor to return to the project. In talking with the designer, we should be able to lighten driving requirements so we don’t have to drive them so deep,” explained Trester.