Culver Storm Water Project Moving Along, Says Schoeff

culver town hall
 
The town of Culver’s storm water project is moving right along, according to Town Manager David Schoeff. He told WKVI the project is now in its design stages, and he’s hoping to have the project out for bids sometime in June.

The project had most recently gone through the drainage board for their approval to work on their drains, and Schoeff said that now that they’ve received that approval, it’s just a matter of making some adjustments on the design. The project’s engineering firm, Commonwealth Engineers, is now working on those changes, and Schoeff said he expects within the next few weeks to have something to review preliminarily before it’s advertised for bids.

The storm water project carries an estimated cost of $892,000, and Schoeff said they’ve received a grant from the Office of Community and Rural Affairs for $792,000, leaving the town with a $100,000 expense. He said the town has had a lot of luck getting grants for projects like these and, hopefully, the luck will continue.

Sewer Separation Project Completed in Winamac

Winamac Town Hall

Members of the Winamac Town Board heard from Commonwealth Engineering representatives Monday night as they reported the final figures from the storm sewer separation project.

The project was finally finished with the separation of several sewer lines in the downtown area and the repaving of some areas in town that were not properly paved in the fall. Stripes have been painted on all the streets and parking lines have also been marked.

The water tower is being painted in the town of Winamac, and that project is expected to be complete by the end of the month. Water pressure has been an issue during this project, but pressure should return to normal when painting is done. This action is done for safety issues and to make any necessary repairs.