At last night’s North Judson-San Pierre School Board meeting, Superintendent Dr. Annette Zupin provided board members with a brief update about a current project that is nearing completion and another project that will be addressed in the near future.
First, she alerted board members that the pool repairs are nearly complete. Employees with the company Buddenbaum & Moore Commercial Pool Services have finished replacing the faulty main drain boxes and pipes have been set. She said this week they are re-tiling. Once all the tile is laid, the curing period will take approximately one month.
“It looks like the end of this year, the beginning of next year, we’ll be swimming in our pool.” She expressed,”We are very confident and happy with the work they’ve done. It’s done right, it’s done well.”
She also mentioned that renovations to the partitions in the restrooms at the Junior/Senior High School will commence over Christmas break. This way, work can be done without interfering with the daily routines of students.