Culver School Board Updated on Project Timeline

The Culver Community School Board received an update on the bond project timeline last week.

The bond projects at the Culver Elementary School include a library renovation, handicap lift for the stage, repaving parking lots, redoing water lines, new boilers, tuckpointing in the masonry, and replacing the gym floor.

Tuckpointing will done at the Middle/High School, along with a FACS (Family and Consumer Science) room renovation, locker room renovation, restroom renovation, band and choir room renovations, gym floor replacement, and the installation of a ramp in the high school auditorium instead of a handicap lift.  Electrical panels will be updated, and pick-up and drop-off in the back of the school building.

Superintendent Karen Shuman said bids for the projects are due Friday, January 27 with a recommendation to the board by SitelogIQ representatives at their February 6 meeting, including all bidding information for each line item of the project. 

Once a bid is approved, Shuman said the construction will move quickly. 

“We anticipate starting in mid-March with the deconstruction of the locker rooms and gyms and bleachers in the high school and a rebuild of those before graduation,” explained Shuman. “We’ll move on to the Elementary School gym and band and choir with all of those happening in mid-May so that we can have everything in place by August 8.”

The school board previously agreed to take out two series of bonds in the amount of $12,050,000 to finance these updates to the school buildings with a slight increase to the tax rate.