PORTER AND LA PORTE COUNTIES, Ind. – Indiana Department of Transportation contractor Milestone Contractors LP will conduct overnight lane closures on I-94 westbound between mile marker 30 and 36 (east and west of U.S. 421) beginning on or after Tuesday, May 5 to set up a new traffic configuration.
Alternating lane closures will occur on I-94 during the hours of 9 p.m. to 5 a.m. Motorists should be prepared for changing traffic layouts during this time. This work is weather dependent and may be rescheduled.
Starting on or after the morning of May 6, the left two lanes of westbound I-94 will be closed for resurfacing with two travel lanes shifted to the right. The ramps at exit 34 for U.S. 421 will remain open. This traffic configuration will be in place for approximately two weeks.
I-94 will maintain two travel lanes in each direction during construction, with lane shifts to accommodate the location of the work zone. Additional overnight lane closures will be used as needed to reconfigure the work zone setup or for other construction tasks.
This construction contract will be conducted over a two-year period and includes five projects:
Asphalt resurfacing on I-94 from 3.09 miles west of U.S. 421 to 0.4 miles east of U.S. 421
Concrete pavement restoration on I-94 from 0.43 miles east of State Road 49 to 3.09 miles west of U.S. 421
Bridge painting on C.R. 500 E over I-94
Bridge painting on County Line Rd (Porter/La Porte) over I-94
Bridge painting on U.S. 421 over I-94
INDOT encourages drivers to consider safety for all by slowing down, using extra caution and driving distraction-free when travelling in and around all work zones.