Starke County Building Corporation to Meet Today

 

The Starke County Building Corporation will meet this morning at 8:30 a.m.

The corporation members will be going over outstanding claims for payment by the commissioners from the construction of the second annex building.

The meeting is set in the Starke County Commissioners meeting room in the Starke County Annex building.

New Starke County Jail Nearing Completion

This building on SR 8 at CR 550 E is part of the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E is part of the new Starke County Sheriff’s Office and Detention Center.

To use a baseball analogy, construction of the Starke County Sheriff’s Department and Detention Center has rounded third base and is heading for home plate. That’s how Dion Katsouros from Skillman Corporation described the project to the Starke County Building Corporation during their monthly meeting. Continue reading

Starke County Officials Planning Jail Grand Opening

This building on SR 8 at CR 550 E is part of the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E is part of the new Starke County Sheriff’s Office and Detention Center.

Starke County officials are making plans for a May 22nd open house to celebrate the completion of the Starke County Sheriff’s Office and Detention Center. Contractors are putting final touches on the new facility east of Knox on State Road 8 and will have the building ready to turn over to the county by May 1st. Continue reading

Starke County Commissioners, Building Corporation to Award Jail Courtroom Bids

This building on SR 8 at CR 550 E is part of the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E is part of the new Starke County Sheriff’s Office and Detention Center.

The Starke County Commissioners are expected to award bids this evening for the interior build-out of the Starke County Jail Courtroom. The commissioners received eight bids for general services and four each for mechanical and electrical work. Representatives from Skillman Corporation took them under advisement at the Jan. 8 bid opening and have reviewed them to make sure they meet the specifications outlined in the project documents. Base bids range from a low of $167,500 to a high of $227,250, with five alternates each. Continue reading

New Starke County Jail Still On Schedule and On Budget

This building on SR 8 at CR 550 E is part of the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E is part of the new Starke County Sheriff’s Office and Detention Center.

Construction of the new Starke County Sheriff’s Office and Detention Center is still on schedule to wrap up next spring. Information shared with the Starke County Building Corporation indicates the metal addition to the rear of the existing building on State Road 8 east of Knox is 80-percent finished. Continue reading

Starke County Sheriff’s Office and Detention Center Takes Shape

This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff’s Office and Detention Center.

The new Starke County Sheriff’s Office and Detention Center east of Knox on State Road 8 is still on schedule for a spring 2015 completion. The project is also on budget and features a number of state-of-the-art amenities like video visitation. Commissioner and Starke County Building Corporation President Kathy Norem says it will be much safer and will cut down on the import of contraband into the jail. Continue reading

Fire Pump Necessary for New Jail Facility

This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff’s Office and Detention Center.

The $29,000 to add a fire pump to the Starke County Sheriff’s Office and Detention Center was money well spent by the Starke County Building Corporation. The project to extend city water lines to the site east of Knox is finished, but the water pressure is still short of what is needed to suppress a fire at the facility. Building corporation members approved that expenditure last month in order to keep the project on track with the additional wiring that would be necessary for the installation. Completion of the new building is still scheduled next spring.

Meanwhile, the committee appointed last month to discuss future uses for the current jail facility is in the very early stages of exploring options. The building will have to be used for something within the scope of corrections since it was used as collateral for the bond to build the new structure. Continue reading

Building Corporation to get Reports on Old, New Jails

Starke County Sheriff's Department
A committee is looking into possible uses for the current Starke County Jail when a new facility east of Knox is completed.

The Starke County Building Corporation is expected to get an update from the committee tasked with looking into future uses of the former jail when they meet this morning. Representatives from Skillman Corporation will also discuss the scope of the old jail renovation as well as share information about how construction of the new facility is going. The building east of Knox on State Road 8 is due to open next spring. The Starke County Building Corporation meeting will take place at 8:30 a.m. at the county annex building prior to the commissioners meeting at 9.

 

Jail Water Line Delay Potentially Costs County $29,000

This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff’s Office and Detention Center.

The Starke County Building Corporation may have been able to save $29,000 had the water line extension from Henry Drive east to the new Starke County Sheriff’s Office and Detention Center been finished by its April 1 deadline.

The existing water lines to the building on State Road 8 at County Road 550 East are not wide enough to provide enough pressure should the building catch on fire. The county and city opted last fall to run new lines to the facility and contract the work out. The Knox City Council accepted a bid from Mark Milo Enterprises to do the work.

Continue reading

Starke County Building Corporation, Commissioners Meeting This Morning

Starke County Courthouse
Starke County Courthouse

The Starke County Building Corporation plans to appoint a committee to discuss future uses for the current jail. They are meeting this morning at 8:30 at the county annex building, prior to the commissioners meeting at 9. Skillman Corporation will also provide an update on how construction of the new jail east of Knox on State Road 8 is going. It’s scheduled for completion in the spring of 2015. The commissioners agenda includes consideration of a proposal from Starke County Clerk Evelyn Skronski to relocate some precincts. Officials from IU Health Starke Hospital will also discuss the physicians recruitment program. EMA Director Ted Bombagetti and James Coad are on the agenda regarding the county’s emergency preparedness plan. Wendy Elam from CADA has a proclamation for the county to declare April Child Abuse Prevention Month. CADA, CASA and the Indiana Department of Child Services are kicking off the awareness campaign tomorrow evening at 7:30 p.m. at the Nancy J. Dembowski Convention Center in downtown Knox with a Pinwheels for Prevention candle lighting ceremony. Members of the public are invited to come show their support for children in the community. In the event of inclement weather, the ceremony will take place inside.

Starke County Sheriff’s Department Project Still On Track

This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff's Office and Detention Center.
This building on SR 8 at CR 550 E will soon house the new Starke County Sheriff’s Office and Detention Center.

The Starke County Building Corporation yesterday morning heard an update on the construction efforts at the new Starke County Sheriff’s Office and Detention Center. According to the progress report presented at the meeting, a number of structure items – as well as those for mechanical, engineering, and plumbing – were completed last month, with more efforts underway this month to continue that work for at least the next four weeks. The report indicated that the work completed within the steel building last month included the continuation of the installation of structural steel and miscellaneous demolition as required. Crews worked on setting the hollow steel metal door and window frames, continued installing interior masonry walls, started metal stud wall framing and drywall installation, and received detention door frames. Continue reading

Starke County Building Corp. Hears Water Line Update

This building on SR 8 at CR 550 E will soon house the new Starke County Jail.
This building on SR 8 at CR 550 E will soon house the new Starke County Jail.
The Starke County Building Corporation yesterday morning heard an update regarding the water line project for the construction of the Starke County Sheriff’s Office and Detention Center. Commissioner Kathy Norem said the work on the water line seems to be languishing; work was done in late December and was paid off, but the contractor has not done any work since.

Continue reading

Starke County Building Corp., Commissioners to Meet This Morning

  
 
The Starke County Building Corporation will meet this morning prior to the regular meeting of the Starke County Commissioners to hear a financial report and the status of the water line project for the soon-to-be-constructed Starke County Sheriff’s Office and Detention Center. A project construction update will also be heard during the meeting of the building corporation from the Skillman Corporation.

Continue reading

Starke County Building Corp. Appoints Lessor Representative

This building on SR 8 at CR 550 E will soon house the new Starke County Jail.
This building on SR 8 at CR 550 E will soon house the new Starke County Jail.
The Starke County Commissioners met in a special session with the building corporation for the construction of the Starke County Sheriff’s Office and Detention Center prior to the commissioner’s regularly scheduled meeting. Commissioner Kathy Norem explained the meeting was necessary in order to appoint a lessor representative to allow them to approve and pay claims.

Continue reading

Starke County Building Corp. Receives A+ Bond Rating

This building on SR 8 at CR 550 E will soon house the new Starke County Jail.
This building on SR 8 at CR 550 E will soon house the new Starke County Jail.

The Starke County Building Corporation recently received its long-term bond rating, and according to commissioner Kathy Norem, the county is very pleased with the result. Standard & Poor’s Rating Services has assigned its “A+” long-term rating and stable outlook to the Building Corporation’s property tax economic development income tax lease rental bonds for the county jail bond rate.