Construction on 7th Road Project Continues

  
 

The 7th Road project in Plymouth should be complete by the end of June.

Project Supervisor Bart Trester from USI Consultants told the Marshall County Commissioners on Monday that the center of the roundabout is open to traffic in order for construction to occur on the east and west third of the circular intersection. Crews will return the traffic pattern to travel around the roundabout when that phase is complete. The project is anticipated to be done by the end of June.

Continue reading

Starke County Highway Department Shifts Focus to Spring Projects

  
 

The Starke County Highway Department’s focus has shifted to spring and summer projects now that the last of the snow is gone. Superintendent Rik Ritzler says drivers are making repairs to roads in their areas that were damaged by thawing frost over the winter. He says they’re patching for now, but a more permanent fix will be made in the next few months as weather allows. Continue reading

Metronet Project Done, 7th Road Project Awaiting Completion

Marshall County Commissioners (L to R) Deb Griewank, Kevin Overmyer and Kurt Garner
Marshall County Commissioners (L to R) Deb Griewank, Kevin Overmyer and Kurt Garner

This week, the Marshall County Commissioners approved and signed paperwork to complete the acceptance of the Metronet project along Glen Overmyer Drive. The work ended on Nov. 12 with all punch list items checked off the list. The installation of conduit for the three phases of the Metronet project is now complete.

The conduit will house dark fiber capable of distributing high-speed internet to business and industry in Plymouth. The conduit was installed in the city limits and along old U.S. 31 through LaPaz, LaVille, Lakeville and into South Bend. LaVille School Corporation and Hoosier Racing Tire have already lit dark fiber to begin using the product.

Continue reading

Weather Delays Jefferson Bridge Opening

Jefferson Street bridge
Jefferson Street bridge

It will take a couple of more days to open the Jefferson Street bridge in Plymouth.

Marshall County Supervisor of County Highways Jason Peters told WKVI News that weather has delayed the completion of bridge work. The projected reopening date is now Wednesday.

Bart Trester from USI Consultants told the Marshall County Commissioners last week that the remaining items on the checklist include sidewalks and curbs. Crews also want to reseal the bridge deck to complete the project.

Continue reading

Jefferson Street Bridge in Plymouth to Close Thursday

Jefferson Street bridge
Jefferson Street bridge

The Jefferson Street bridge in Plymouth will be closing beginning Thursday.

Michael Obergfell from USI Consultants told the Marshall County commissioners Monday morning that the concrete slabs by the bridge are not stable and the sidewalk is not reinforced. The bridge was rehabilitated in 1986 but a storm sewer line is leaking and may be causing stability issues.

Obergfell suggested that the commissioners close the bridge so crews can immediately fix the issue.

Continue reading