The commissioners reviewed quotes for a drainage and sidewalk project around the Starke County Courthouse.
Continue readingHamlet’s Railroad Street Project Officially Wrapped Up
Hamlet’s Railroad Street project is officially complete. Engineer Lee Nagai is pleased with how it turned out. “I think it’s where everyone is happy to know that it’ll be under-budget and ahead of schedule,” he says.
Continue readingRailroad Street Construction to Start After County Fair
Upgrades to Railroad Street in Hamlet will have to wait until after the Starke County Fair. Engineer Lee Nagai told the town council Tuesday that all the contracts have been signed, and paving contractor Mark Milo tentatively plans to start the week after the fair.
Continue readingHamlet’s Railroad Street Project Experiences Slight Delay
The Town of Hamlet is still waiting for the start of its Railroad Street project. Engineer Lee Nagai told the town council Wednesday that the contractor is behind on its projects, due to recent weather. “He told me the paver is talking about the middle of July, so as soon as I get a firm schedule on when they could be here with the asphalt, then we’ll back everything up,” Nagai explained.
Continue readingHamlet Council Updated on Railroad Street Project Preparations
Preparations continue for Hamlet’s Railroad Street project. Engineer Lee Nagai gave an update to the town council Wednesday.
Continue readingHamlet’s Railroad Street Project to Start As Soon As Contract is Finalized
Hamlet’s Railroad Street project is set to begin soon. Last month, the town council awarded a bid to Mark Milo Enterprises. The town received a Community Crossings grant from the state to cover 75 percent of the cost.
Continue readingHamlet Town Council Awards Bid for Railroad Street Project
The Town of Hamlet has chosen a paving contractor for its upcoming Railroad Street project. The town council approved a bid from Mark Milo Enterprises during a special session Wednesday, according to Clerk-Treasurer Kristina Pitts. At just under $194,000, Pitts says it was the lowest of the three bids the town received.
Continue readingKnox Board of Works Considers Demolition Bid
The Knox Board of Works members opened a single bid for the demolition of 313 Ostrander Court when they met last week.
Continue readingHamlet Council Decides to Hold Off on Railroad Street Grant Application until January
Knox Board of Works Members Consider Bids for Blighted Structure on Pearl Street
Some confusion over bid specifications led to drastically different offers being opened at the Knox Board of Works meeting on Monday.
The bids were for demolition work on the blighted structure at 202 N. Pearl Street.
The first bid that was opened came in from Jackson Truck and Excavating and it was for $33,900. The second bid was from Mark Milo Enterprises for $14,900. The reason for the difference was that Jackson included the price for asbestos removal, while Milo did not. Continue reading
Knox Board of Works Grants Conditional Blight Elimination Contract
The effort to tear down dilapidated houses within the Knox city limits took another step forward yesterday during a special-called Board of Works meeting. Members opened three bids for the demolition of four more houses with money from a blight elimination grant from the Indiana Housing & Community Development Authority. Continue reading
Loose Ends Remain with Water Line Project
The Knox City Council last week received an update on the Henry Drive water extension project.
Mayor Rick Chambers stated that while the project is complete there are several loose ends that need to be tied.
“The Henry Drive water line is complete. The street has been paved and one homeowner was not happy with the way his yard was left and I’ll take care of that. Territorial Engineering is still working with Milo to move that original water line because the water superintendent didn’t like the way it was placed. Territorial will be paying that bill. They want to wait until later on this summer when the water levels drop a little bit. That will be taken care of,” explained Chambers.
Water Line Project for New Jail Complete
The Knox Board of Public Works received an update on the water project for the new Starke County Sheriff’s Office and Detention Center.
Knox Mayor Rick Chambers said the project should be complete today.
“The weather has finally broken so we have gotten caught up,” explained Chambers. “The contractor has gotten in there and pretty much finished his job. The water line has been de-sanitized and pressure checked. There will be some additional work to be done. The line will have to be moved – it’s been deflected too much so we will go in and correct that problem, but should be up and operational within the next day or so.”
Jail Water Line Delay Potentially Costs County $29,000
The Starke County Building Corporation may have been able to save $29,000 had the water line extension from Henry Drive east to the new Starke County Sheriff’s Office and Detention Center been finished by its April 1 deadline.
The existing water lines to the building on State Road 8 at County Road 550 East are not wide enough to provide enough pressure should the building catch on fire. The county and city opted last fall to run new lines to the facility and contract the work out. The Knox City Council accepted a bid from Mark Milo Enterprises to do the work.
Knox City Council Approves Easement Agreement
The Knox City Council approved an easement agreement with Chuck and Dennis Estok to move forward with the water line project for the Starke County Sheriff’s Department and Detention Center at the intersection of State Road 8 and County 550 East in Knox.
The city of Knox will be responsible for the installation the water lines for the project that will extend to the property from Henry Drive.
Knox Board of Public Works Discusses Progress at Phoenix House
The Knox Board of Public Works approved a pay application for Chester Construction at their meeting this week in the amount of $49,563.74. The board members also approved a claim for Mark Milo Enterprises for $29,307.50.
Van Janovic from Territorial Engineering explained to the board that these claims are for the Phoenix House construction project. He said Chester’s work is about 91 percent complete and the parking lot work being done by Mark Milo is about 63 percent complete. He said he walked through the project area and was impressed with the work that has been done and it’s been on schedule.