Upgrades to North Judson’s wastewater facilities are now complete. The town council approved the certificate of substantial completion last week, along with final pay applications.
Continue readingNorth Judson Council Chooses Town & Country for Franklin and Main Street Paving
Paving work on Franklin and Main streets in North Judson could be complete by the end of the month. The town council last week chose Town & Country Paving to do the work at a cost of just under $186,000.
Continue readingNorth Judson Council Approves Change Order for Sewer Project Paving Work
The North Judson Town Council has finalized a financial adjustment for the town’s wastewater project. Initially, there was money in the project budget to cover road patching on Franklin and Main streets once sewer work wraps up there, but town officials have since decided to do the work separately.
Continue readingNorth Judson Storm Sewer Installation Wrapping Up
North Judson’s wastewater project continues to move along. Sarah Prizio with Commonwealth Engineers told the town council last week that crews had finished installing the storm sewer along Railroad and Franklin streets, while work on the portion on Main Street was wrapping up.
Continue readingNorth Judson Town Council Approves Wastewater Project Change Orders
North Judson’s wastewater project is expanding slightly. The town council approved a pair of change orders last week.
Continue readingNorth Judson Town Council Receives Update on Wastewater Project
The water project in North Judson is wrapping up just as the wastewater project is getting started.
As previously reported, this project will involve the installation of a new sewer dedicated to stormwater, rehabilitation of the existing wastewater collection system and upgrades to the wastewater treatment plant will also be made.
Continue readingNorth Judson Water Tower Rehabilitation Project Moves Downtown
Water tower upgrades continue in North Judson. Clerk-Treasurer Andrew Rowe says the focus is now shifting to the downtown water tower.
Continue readingNorth Judson Wastewater Improvement Project Gets Closer to Construction Phase
An update on the North Judson’s wastewater treatment plant project was provided to Town Council members when they met Monday night.
Continue readingNorth Judson Town Council Receives Project Updates from CommonWealth Engineers
Updates over the Town of North Judson’s water and wastewater projects were provided at Monday night’s council meeting.
Continue readingWastewater Project Update Provided to North Judson Town Council Members
Contract bids for the North Judson Combined Sewer Overflow (CSO) Wastewater project will be accepted until Monday, May 6th.
Continue readingNJ Town Council Updated on Water and Wastewater Projects
North Judson Town Council members were given an update about their water and wastewater projects when they met Monday night.
Continue readingAlternative Well Plan Presented to North Judson Town Council Members
Project officials are addressing concerns over plans for an above-ground well enclosure at Norwayne Field.
Project Engineer Rob Bellucci from CommonWealth Engineers came before the North Judson Town Council last week with a proposed project amendment.
Continue readingNJ Town Council Approves Amended Owner-Engineer Agreement for Drinking Water and Wastewater Projects
North Judson Town Council members approved an amended version of the owner-engineer agreement with CommonWealth Engineers when they met Monday night.
Project Engineer Rob Bellucci spoke on behalf of the firm. He alerted members that since the base agreement only covered the services provided for the environmental report, an amendment had to be made in order for the agreement to encompass other aspects of the projects. Continue reading
North Judson Town Council Approves Reimbursement Resolutions
The approval of two resolutions by North Judson Town Council members Monday night will allow the town to be reimbursed for expenditures made toward the water and sewer projects prior to the completion of the bonding process. Continue reading