Culver Town Council Receives Update on Amphitheater Project

Construction on the Lake Maxinkuckee Amphitheater could be complete by the Memorial Day holiday in 2018.

Mike Reese from the Troyer Group gave the Culver Town Council members a timeline for the bidding process and construction.

“It goes out to bid right after the holidays and bids will be opened in late January,” said Reese. “You’ll award a contract so a contractor can get started as soon as weather allows in the spring. The goal would be to be done by mid-May or Memorial Day weekend so by the time the summer rolls around the amphitheater will be ready to go.”

Plans call for the amphitheater to be constructed in the town park. The project calls for a covered stage and four rows of tiered grass seating with concrete retaining walls. Additional open seating areas would be available around the stage and under trees.