Pulaski County Highway Superintendent Mark Fox informed the commissioners this week that there are three bridges on the 12-month inspection cycle. Work will be done soon to remove them from that list.
“We’re going to place wrap underneath these bridges to correct a substructure undercutting issue and those three will be able to be removed from that 12 month inspection cycle once we complete that,” stated Fox.
The Pulaski County Commissioners have a tough decision on their hands after a family relocated by the Bridge 291 project submitted receipts for expenses after their deadline. Jeff Larrison with United Consulting told the commissioners that they have already paid $78,546 to the Combs family for expenses incurred by their relocation following the county’s acquisition of their parcel, but the family recently submitted receipts for $19,468 worth of expenses after the receipt deadline of Aug. 21, 2013.
The Monterey Bridge project is nearing completion.
While the weather has not played into the construction crew’s favor, it is expected to finish up by Thanksgiving. Jeff Larrison from United Consulting said a ribbon cutting ceremony will be held to formally end the project and that will be set after the 8th of November.
The deadline for relocation expenses stemming from the Monterey Bridge construction project has come and gone, according to United Consulting’s Jeff Larrison. He told the county commissioners that he received a notice explaining the the deadline has passed and some expenses still had not been turned in, raising the question of whether or not the commissioners would like to still allow those expenses to be filed.
Bret Smiley, construction manager with United Consulting, told WKVI that concrete has been poured this week. The rail wall, the bridge deck and approaches have been poured. He said he did testing and it was the smoothest concrete pour that he’s been privy to.
The Monterey Bridge Project is expected to be completed before the Nov. 29 completion date.
Bret Smiley, construction manager with United Consulting, said the construction crews have installed the Stay-in-Place metal decking. Continue reading →
After a few weeks of battling high water issues, the crew working on the Monterey Bridge project is moving right along.
Bret Smiley of United Consulting reported that the beams have been set and the crews are placing decking at this juncture of the project. Overhang jacks are being installed along the outside beams and they are installing decking on them as well. Once the deck is completely prepared, the next step will be the placement of rebar throughout the deck.
The project appears to be on schedule and the project should be completed in October.
The bridge inspections for Pulaski County have been completed. According to Jeff Larrison and Matt Lee of United Consulting, 73 routine bridge inspections have been completed this year and the pair presented the report to the county commissioners at their meeting Monday night.
The storms that rolled through the Pulaski County area last week did affect the Monterey Bridge project.
Bret Smiley, construction manager with United Consulting, said that work has halted on the project for this week as flooding was an issue. A contractor will be on-site to clear water from the area today or tomorrow to prepare for more concrete work on Monday.
The Monterey Bridge project is moving along despite the water issues experienced in April.
Bret Smiley, construction manager with United Consulting, said there was a bit of a flooding issue at the southern end of the bridge project, but that isn’t affecting the work being done this week on the north side of the bridge. The south side of the bridge project had been underwater and the workers have been working around that issue. LaPorte Construction built up a makeshift berm to help with erosion issues and to push back the river water.
Rain dates were built into the original construction schedule so Smiley noted the project is on schedule. They are drive piling the north side of the bridge so beams can be set this week and situating the crane so it can safely operate. Smiley said the ground is swelled with water and unstable so they are creating a safe platform for the crane.
Smiley said the retaining walls will be built in the next week or so.
The Monterey Bridge project is expected to begin once the weather breaks.
Jeff Larrison of United Consulting, the company involved in the engineering and planning for the project, said a pre-construction meeting with the Indiana Department of Transportation is set for Thursday, March 7 to discuss details of the project and set a start date. All of the paperwork has been submitted and contracts have been signed for the construction. A start date is the only issue left to be decided.
A new bridge will be constructed adjacent to the old bridge in Monterey. Bridge 291 has been deemed a historic structure so the new bridge will not be demolished. Larrison will report a construction date when it is decided next week.
The Pulaski County Commissioners this week signed a revised contract for the inspection of the Monterey Bridge. Jeff Larrison of United Consulting told the commissioners this week that the original construction cost estimate came in at around $1.55 million, but the bids came in lower than expected, prompting a new revision to the inspection contract with a lower price.
Efforts to restore bridges in Pulaski County continue as the commissioners this week discussed the possibility of yet another bridge to work on. Jeff Larrison of United Consulting told the commissioners that he had put together an engineer’s report for Bridge 268, which is in dire need of a new deck. This project, he says, will be a lot cheaper and a bit easier than the complete replacement of Bridge 291 in Monterey.
Larrison says the bridge would be restored rather than completely replaced, and no land acquisition is necessary.
Jeff Larrison of United Consulting presented the Pulaski County Commissioners with an update on the Bridge 291 project this week.
The last two expenses for the Combs property, which was acquired as part of the construction project, were presented to the commissioners. The Combs property was acquired and their moving expenses were paid in accordance with INDOT guidelines, which allow up to $25,000 to be paid to the owners of a property that are required to relocate.
The Pulaski County Commissioners received an update yesterday regarding the status of the Bridge 291 project. Jeff Larrison of United Consulting told the commissioners that the right-of-ways have been cleared through INDOT, and the necessary documents have been submitted, however, INDOT has pushed several projects back to October.
Larrison said that the county has met all the deadlines, but they have to play by INDOT’s rules – which means opening bids for construction of the new bridge will not take place until October, setting them back several months. Larrison explained that after the bid is let, there is a 30 – 45 day period to choose a winning bid, which means construction could be delayed to as late as November.
Because of this delay, Larrison says a minimal amount of construction will take place before winter, but the majority of the work will take place come spring.
The Pulaski County Commissioners this week received another update on the Bridge 291 project, in which Jeff Larrison of United Consulting informed them that the next step in the process is to approve the construction inspection agreement. He says the agreement will go to the Indiana Department of Transportation, which will then review the rates for inspection and approve them if acceptable.
As with the rest of the project, 80 percent of this expense would be covered by INDOT, while the county would cover the other 20 percent. The cost of $194,800 for the inspection makes up 12.5 percent of the total construction cost as allotted by INDOT.
Jeff Larrison of United Consulting gave the Pulaski County Commissioners an update on the Bridge 291 project.
According to Larrison, INDOT will issue credit for up to 50 percent of the county’s 20 percent match for the project, bringing back $345,000 to the county. Larrison also told the commissioners that they will have to pay some of that money to businesses that have to move because of the bridge construction, including $8400 for reestablishment of the business and up to $13,000 for moving expenses, as some businesses have heavy equipment that must be moved. The business owners will have to submit invoices to ensure the money is spent correctly.
Another slight hiccup in the Monterey Bridge project was brought before the Pulaski County Commissioners yesterday, as Jeff Larrison from United Consulting announced a small slip of land would cost the county $329 more than previously expected.
The commissioners previously agreed to offer the landowners $900 for a small, previously overlooked sliver of land near the riverbank, but the landowners have countered with a request for $1229. Larrison explained that the increased cost comes from the landowners’ desire to sell the entire parcel of land, rather than a significant chunk.
Jeff Larrison of United Consulting and Pulaski County Highway Superintendent Kenny Becker told the Pulaski County Commissioners this week that they expect a delay in the construction process of the Monterey Bridge Project because of a delay with the INDOT agreement. Larrison explained that INDOT has pushed bid letting for projects throughout the state back several months and as a result, the Monterey Bridge project is expected to be let for bid in September—a two-month setback from their planned letting in July.