The wind turbine project has been delayed at the West Central School Corporation.
“The components that are coming from Germany are here, but the tower itself is being manufactured in Tennessee. That component is being delayed as far as the manufacturing date. I think they had some issues at their factory so we’ve been pushed back to the week of January 9th,” said Superintendent Charles Mellon.